<<Prev Rule

Texas Administrative Code

Next Rule>>
TITLE 16ECONOMIC REGULATION
PART 2PUBLIC UTILITY COMMISSION OF TEXAS
CHAPTER 25SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS
SUBCHAPTER ECERTIFICATION, LICENSING AND REGISTRATION
RULE §25.101Certification Criteria

(a) Definitions. The following words and terms, when used in this section, have the following meanings unless the context indicates otherwise:

  (1) Construction or extension--Does not include the purchase or condemnation of real property for use as facility sites or right-of-way. Acquisition of right-of-way must not be deemed to entitle an electric utility to the grant of a certificate of convenience and necessity without showing that the construction or extension is necessary for the service, accommodation, convenience, or safety of the public.

  (2) Generating unit--Any electric generating facility. This section does not apply to any generating unit that is ten megawatts or less and is built for experimental purposes only.

  (3) Habitable structures--Structures normally inhabited by humans or intended to be inhabited by humans on a daily or regular basis. Habitable structures include, but are not limited to: single-family and multi-family dwellings and related structures, mobile homes, apartment buildings, commercial structures, industrial structures, business structures, churches, hospitals, nursing homes, and schools.

  (4) Municipal Power Agency (MPA)--Agency or group created under Texas Utilities Code, Chapter 163 - Joint Powers Agencies.

  (5) Municipal Public Entity (MPE)--A municipally owned utility (MOU) or a municipal power agency.

  (6) Prudent avoidance--The limiting of exposures to electric and magnetic fields that can be avoided with reasonable investments of money and effort.

  (7) Tie line--A facility to be interconnected to the Electric Reliability Council of Texas (ERCOT) transmission grid by a person, including an electric utility or MPE, that would enable additional power to be imported into or exported out of the ERCOT power grid.

(b) Certificates of convenience and necessity for new service areas and facilities. Except for certificates granted under subsection (e) of this section, the commission will grant an application and issue a certificate only if it finds that the certificate is necessary for the service, accommodation, convenience, or safety of the public, and complies with the statutory requirements in the Public Utility Regulatory Act (PURA) §37.056. The commission may issue a certificate as applied for, or refuse to issue it, or issue it for the construction of a portion of the contemplated system or facility or extension thereof, or for the partial exercise only of the right or privilege. The commission will render a decision approving or denying an application for a certificate within one year of the date of filing of a complete application for such a certificate, unless good cause is shown for exceeding that period. A certificate, or certificate amendment, is required for the following:

  (1) Change in service area. Any certificate granted under this section must not be construed to vest exclusive service or property rights in and to the area certificated.

    (A) Uncontested applications: An application for a certificate under this paragraph must be approved administratively within 80 days from the date of filing a complete application if:

      (i) no motion to intervene has been filed or the application is uncontested;

      (ii) all owners of land that is affected by the change in service area and all customers in the service area being changed have been given direct mail notice of the application; and

      (iii) commission staff has determined that the application is complete and meets all applicable statutory criteria and filing requirements, including, but not limited to, the provision of proper notice of the application.

    (B) Minor boundary changes or service area exceptions: Applications for minor boundary changes or service area exceptions must be approved administratively within 45 days of the filing of the application provided that:

      (i) every utility whose certificated service area is affected agrees to the change;

      (ii) all customers within the affected area have given prior consent; and

      (iii) commission staff has determined that the application is complete and meets all applicable statutory criteria and filing requirements, including, but not limited to, the provision of proper notice of the application.

  (2) Generation facility.

    (A) In a proceeding involving the purchase of an existing electric generating facility by an electric utility that operates solely outside of ERCOT, the commission will issue a final order on a certificate for the facility not later than the 181st day after the date a request for the certificate is filed with the commission under PURA §37.058(b).

    (B) In a proceeding involving a newly constructed generating facility by an electric utility that operates solely outside of ERCOT, the commission will issue a final order on a certificate for the facility not later than the 366th day after the date a request for the certificate is filed with the commission under PURA §37.058(b).

    (C) An electric utility operating solely outside of the ERCOT region may, but is not required to, obtain a certificate to install, own, or operate a generation facility with a capacity of 10 megawatts or less.

  (3) Electric transmission line. All new electric transmission lines must be reported to the commission in accordance with §25.83 of this title (relating to Transmission Construction Reports). This reporting requirement is also applicable to new electric transmission lines to be constructed by an MPE seeking to directly or indirectly construct, install, or extend a transmission facility outside of its applicable boundaries. For an MOU, the applicable boundaries are the municipal boundaries of the municipality that owns the MOU. For an MPA, the applicable boundaries are the municipal boundaries of the public entities participating in the MPA.

    (A) Determination of need:

      (i) Economic projects. Except as otherwise stated in this subparagraph, the following must be met for a transmission line in the ERCOT region. The applicant must present an economic cost-benefit study that analyzes the transmission project under a congestion cost savings test and a production cost savings test. The commission will give great weight to such a study if it is conducted by the ERCOT independent system operator. Adequately quantifiable and ongoing direct and indirect costs and benefits to the transmission system attributable to the project may be included in the cost-benefit study.

        (I) Congestion cost savings test. ERCOT, in consultation with commission staff, must develop a congestion cost savings test.

          (-a-) The congestion cost savings test must include an analysis of whether the levelized ERCOT-wide annual congestion cost savings attributable to the proposed project are equal to or greater than the average of the first three years annual revenue requirement of the proposed project of which the transmission line is a part.

          (-b-) Prior to the effective date of the test developed by ERCOT under this subclause ERCOT may immediately, without updating its current protocols, utilize the generator revenue reduction test, effective Dec. 1, 2011 under ERCOT Nodal Protocols §3.11.2(6), as the congestion cost benefit test required under this clause. ERCOT may continue to rely upon completed calculations using the generator revenue reduction test to evaluate ongoing applications after the effective date of the test developed under this subclause.

        (II) Production cost savings test. The production cost savings test must include an analysis of whether the levelized ERCOT-wide annual production cost savings attributable to the proposed project are equal to or greater than the first-year annual revenue requirement of the proposed project of which the transmission line is a part.

        (III) Economic cost-benefit analysis must be studied for the projected in-service date of the project using the study case identified in the ERCOT planning guide.

        (IV) ERCOT may recommend, and the commission may approve, a transmission line in the ERCOT region that demonstrates a savings under either a congestion cost savings test or a production cost savings test.

      (ii) Reliability projects.

        (I) The requirements of clause (i) of this subparagraph do not apply to an application for a transmission line that is necessary to meet state or federal reliability standards, including: a transmission line needed to interconnect a transmission service customer or end-use customer; or needed due to the requirements of any federal, state, county, or municipal government body or agency for purposes including, but not limited to, highway transportation, airport construction, public safety, or air or water quality.

Cont'd...

Next Page

Link to Texas Secretary of State Home Page | link to Texas Register home page | link to Texas Administrative Code home page | link to Open Meetings home page