TITLE 16ECONOMIC REGULATION
PART 1RAILROAD COMMISSION OF TEXAS
CHAPTER 3OIL AND GAS DIVISION
RULE §3.95Underground Storage of Liquid or Liquefied Hydrocarbons in Salt Formations

      (iii) designed for the permitted maximum allowable operating pressure on the hydrocarbon side of the well; and has an internal diameter of less than or equal to two inches; and an attendant is posted at the well site to provide immediate manual shut-in when in use.

    (D) Fresh water piping designed for the permitted maximum allowable operating pressure on the hydrocarbon side of the well and with an internal diameter of less than or equal to two inches is exempt from the requirement that an emergency shutdown valve be located on the wellhead or separated from the wellhead by a spool no longer than six feet.

  (4) Overfill detection and automatic shut-in methods.

    (A) The requirements of this paragraph shall not apply to an underground hydrocarbon storage facility storing only crude oil.

    (B) The requirements of this paragraph shall not apply to a storage well that is out of service and disconnected from surface piping until the well is reconnected for hydrocarbon storage.

    (C) Within one year of the effective date of this section, each storage cavern shall have at least two of the following redundant devices or methods in operation:

      (i) a safety casing or annular tubing string filled with a non-volatile fluid and equipped with a pressure sensor switch set to automatically close all emergency shutdown valves in response to a preset pressure;

      (ii) a preset pressure sensor switch or transducer on the brine piping that is set to automatically close all emergency shutdown valves in response to a preset pressure. This pressure sensor or transducer may be used in conjunction with weep hole(s) on a safety string that is concentric with the brine string, or in conjunction with weep hole(s) on the brine string;

      (iii) a device on the brine string or brine piping that detects hydrocarbon in the brine by physical or chemical characteristics and that is set to automatically close all emergency shutdown valves in response to hydrocarbon detection;

      (iv) an instrument that detects a rapid increase in the brine flow rate indicative of hydrocarbon in the brine and that is set to automatically close all emergency shutdown valves in response to a preset flow rate or differential flow rate; or

      (v) an alternate device or method approved by the Commission or its designee.

  (5) Leak detectors.

    (A) The provisions of subparagraphs (B) - (D) of this paragraph shall not apply to underground hydrocarbon storage facilities storing only crude oil.

    (B) A leak detector shall be installed and in operation at the wellhead of each hydrocarbon storage well and at each process and transfer area and each surface vessel area that contains liquid or liquefied hydrocarbons. These leak detectors shall be integrated with the warning system required in paragraph (13)(A) of this subsection.

    (C) Leak detectors shall be installed and in operation at four locations that are evenly spaced around the perimeter of the brine pit(s).

    (D) Leak detectors shall be tested twice each calendar year at intervals not to exceed 7 1/2 months and, when defective, repaired or replaced within 10 days.

  (6) Brine system gas vapor control.

    (A) The provisions of this paragraph shall not apply to underground hydrocarbon storage facilities storing only crude oil.

    (B) Gas vapor control devices shall be installed and in operation at each brine pit system to ignite or capture hydrocarbon vapors that are heavier than air. Control devices shall consist of at least one of the following:

      (i) a flare on the brine system upstream from the brine discharge point;

      (ii) a hydrocarbon liquid knockout vessel and degasifier;

      (iii) pilot lights on the berm of each brine pit; or

      (iv) an alternative method designed to provide a reliable, localized point of ignition to prevent the formation of a vapor cloud.

    (C) Brine system gas vapor control systems shall be inspected twice each calendar year at intervals not to exceed 7 1/2 months.

  (7) Fire detection devices or methods and fire control systems.

    (A) Fire detection devices or methods shall be installed and in operation at all process and transfer areas. Fire detection devices or methods specified in this paragraph shall be integrated with the warning system required in paragraph (13)(A) of this subsection. Fire detection shall consist of at least one of the following:

      (i) fire detectors;

      (ii) heat sensors, including meltdown and fused devices; or

      (iii) camera surveillance at facilities that are attended at an on-site control room 24 hours per day.

    (B) Fire detectors shall be tested twice each calendar year at intervals not to exceed 7 1/2 months and, when defective, repaired or replaced within 10 days.

    (C) Within three years of the effective date of this section, each storage wellhead in active storage service shall have fire suppression capability designed to aid in personnel rescue and for equipment protection and cooling. Within one year of the effective date of this section, the operator may request an exception to the schedule or fire suppression requirement of this subparagraph and propose an alternative schedule or means of protection from wellhead fire for approval of the Commission or its designee.

  (8) Emergency response plan. Each storage facility shall submit to the Commission a written emergency response plan. The plan shall address spills and releases, fires, fire suppression capability, explosions, loss of electricity, and loss of telecommunication services. The plan shall describe the storage facility's emergency response communication system, procedures for coordination of emergency communication and response activities with local emergency planning committees and other local authorities, use of warning systems, procedures for citizen and employee emergency notification and evacuation, and employee training. The initial plan must be designed based upon the existing safety measures at the facility. The plan shall be updated as changes in safety features at the facility occur, or as the Commission or its designee requires. The plan shall include a plat of the facility that shows the location of wells, processing areas, loading racks, brine pits, and other significant features at the site. A copy of the plan shall be provided to the local emergency response planning committee and to any other local governmental entity that submits a written request for a copy of the plan to the operator. Copies of the plan shall also be available at the storage facility and at the company headquarters.

  (9) Notification of emergency or uncontrolled release.

    (A) Emergency response personnel. Each operator shall notify the county sheriff's office, the county emergency management coordinator, and any other appropriate public officials, which are identified in the emergency response plan, of any emergency that could endanger nearby residents or property. Such emergencies include, but are not limited to, an uncontrolled release of hydrocarbons from a storage well, or a leak or fire at any area of the storage facility. The operator shall give notice as soon as practicable following the discovery of the emergency. At the time of the notice, the operator shall report an assessment of the potential threat to the public.

    (B) Commission. The operator shall report to the appropriate Commission district office as soon as practicable any emergency, significant loss of fluids, significant mechanical failure, or other problem that increases the potential for an uncontrolled release. The operator shall file with the Commission within 30 days of the incident a written report on the root cause of the incident. The operator shall file with the Commission within 90 days of the incident a written report that describes the operational changes, if any, that have been or will be implemented to reduce the likelihood of a recurrence of a similar incident. An operator may request that the Commission grant, for good cause, a reasonable amount of additional time to file a written report on the root cause of the incident.

  (10) Public education. Each facility operator shall establish a continuing educational program to inform residents within a one-mile radius of a hydrocarbon storage facility of emergency notification and evacuation procedures.

  (11) Annual emergency drill. Annually, each operator shall conduct a drill that tests response to a simulated emergency. Written notice of the drill shall be provided to the appropriate Commission district office, the county emergency management coordinator, and the county sheriff's office at least seven days prior to the drill. Local emergency response authorities shall be invited to participate in all such drills. The operator shall file a written evaluation of the drill and plans for improvements with the appropriate district office and the county emergency management coordinator within 30 days after the date of the drill.