<<Prev Rule

Texas Administrative Code

Next Rule>>
TITLE 30ENVIRONMENTAL QUALITY
PART 1TEXAS COMMISSION ON ENVIRONMENTAL QUALITY
CHAPTER 334UNDERGROUND AND ABOVEGROUND STORAGE TANKS
SUBCHAPTER CTECHNICAL STANDARDS
RULE §334.50Release Detection

      (iii) Piping installed or replaced on or after January 1, 2009. In addition to the required line leak detector prescribed in clause (i) of this subparagraph, each pressurized pipe shall also be tested or monitored for releases at least once every 30 days by using interstitial monitoring as prescribed in subsection (d)(7) of this section as the primary release detection method no later than September 1, 2018.

    (B) Requirements for suction piping and gravity flow piping.

      (i) Piping installed prior to January 1, 2009. Except as provided in clause (iii) of this subparagraph, each separate pipe in a UST piping system that conveys regulated substances either under suction or by gravity flow shall meet at least one of the following requirements.

        (I) Each separate pipe may be tested at least once every three years by means of a positive or negative pressure tightness test applicable to underground product piping and conducted in accordance with a code or standard of practice developed by a nationally recognized association or independent testing laboratory. Any such piping test shall be capable of detecting any release from the piping system of 0.1 gallons per hour.

        (II) Each pipe may be monitored for releases at least once every 30 days by using one or more of the release detection methods prescribed in subsection (d)(5) - (10) of this section.

      (ii) Piping installed or replaced on or after January 1, 2009. Except as provided in clause (iii) of this subparagraph, each suction line shall be tested or monitored for releases at least once every 30 days by using interstitial monitoring as prescribed in subsection (d)(7) of this section as the primary release detection method no later than September 1, 2018.

      (iii) No release detection methods are required to be installed or applied for any piping system that conveys regulated substances under suction when such suction piping system is designed and constructed in accordance with the following standards:

        (I) the below-grade piping operates at less than atmospheric pressure;

        (II) the below-grade piping is sloped so that all the contents of the pipe will drain back into the storage tank if the suction is released;

        (III) no more than one check valve is included in each suction line;

        (IV) the check valve is located aboveground, directly below and as close as practical to the suction pump; and

        (V) verification that the requirements under subclauses (I) - (IV) of this clause have been met can be provided in the form of:

          (-a-) signed as-built drawings or plans provided by the installer or by a professional engineer who is duly licensed to practice in Texas; or

          (-b-) signed written documentation provided by a UST contractor who is properly registered with the agency, by a UST installer who is properly licensed with the agency, or by a professional engineer who is duly licensed to practice in Texas.

    (C) Monitoring secondary containment. In addition to the requirements in subparagraphs (A) and (B) of this paragraph, all piping in a hazardous substance UST system shall also be equipped with a secondary containment system and related release detection equipment, as prescribed in subsection (c) of this section.

(c) Additional release detection requirements for hazardous substance UST systems. In addition to the release detection requirements for all UST systems prescribed in subsections (a) and (b) of this section, owners and operators of all hazardous substance UST systems shall also assure compliance with the following additional requirements.

  (1) All new hazardous substance UST systems shall be in compliance with the requirements of paragraph (3) of this subsection for the entire operational life of the system.

  (2) All existing hazardous substance UST systems shall be brought into compliance with the requirements of paragraph (3) of this subsection no later than December 22, 1998.

  (3) Secondary containment. All hazardous substance UST systems (including tanks and piping) shall be equipped with a secondary containment system which shall be designed, constructed, installed, and maintained in accordance with §334.45(d) and §334.46(f) of this title (relating to Technical Standards for New Underground Storage Tank Systems; and Installation Standards for New Underground Storage Tank Systems).

  (4) Release detection.

    (A) All hazardous substance UST systems (including tanks and piping) installed prior to January 1, 2009, shall include one or more of the release detection methods or equipment prescribed in subsection (d)(7) - (10) of this section, which shall be capable of monitoring the space between the primary tank and piping walls and the secondary containment wall or barrier.

    (B) All hazardous substance UST systems (including tanks and piping) installed on or after January 1, 2009, shall be monitored by using interstitial monitoring as prescribed in subsection (d)(7) of this section as the primary release detection method no later than September 1, 2018.

(d) Allowable methods of release detection. Tanks in a UST system may be monitored for releases using one or more of the methods included in paragraphs (2) - (10) of this subsection. Piping in a UST system may be monitored for releases using one or more of the methods included in paragraphs (5) - (10) of this subsection. Any method of release detection for tanks and/or piping in this section shall be allowable only when installed (or applied), operated, calibrated, and maintained in accordance with the particular requirements specified for such method in this subsection.

  (1) Tank tightness and inventory control requirements. A combination of tank tightness testing and inventory control may be used as a tank release detection method only until December 22, 1998, subject to the following conditions and requirements.

    (A) Tank tightness test. Any tank tightness test shall be conducted in conformance with the following standards.

      (i) The tank tightness test shall be conducted in accordance with a code or standard of practice developed by a nationally recognized association or independent testing laboratory.

      (ii) The tank tightness test shall be performed by qualified personnel who possess the requisite experience, training, and competence to conduct the test properly, who are present at the facility and who maintain responsible oversight throughout the entire testing procedure, and who have been certified by the manufacturer or developer of the testing equipment as being qualified to perform the test. The tank tightness test shall be conducted in strict accordance with the testing procedures developed by the system manufacturer or developer.

      (iii) The tank tightness test shall be capable of detecting a release of 0.1 gallons per hour from any portion of the tank which contains regulated substances.

      (iv) The tank tightness test shall be performed in a manner that will account for the effects of vapor pockets, thermal expansion or contraction of the stored substance, temperature of the stored substance, temperature stratification, evaporation or condensation, groundwater elevation, pressure variations within the system, tank end deflection, tank deformation, and any other factors that could affect the accuracy of the test procedures.

    (B) Inventory control. All inventory control procedures shall be in conformance with the following requirements.

      (i) All inventory control procedures shall be in accordance with a code or standard of practice developed by a nationally recognized association or independent testing laboratory, such as American Petroleum Institute Publication 1621, "Bulk Liquid Stock Control at Retail Outlets;" and

      (ii) Reconciliation of detailed inventory control records shall be conducted at least once every 30 days, and shall be sufficiently accurate to detect a release as small as the sum of 1.0% of the total substance flow-through for the 30-day period plus 130 gallons.

      (iii) The operator shall assure that the following additional procedures and requirements are followed.

        (I) Inventory volume measurement for regulated substance inputs, withdrawals, and the amount still remaining in the tank shall be recorded each operating day.

        (II) The equipment used shall be capable of measuring the level of stored substance over the full range of the tank's height to the nearest 1/8 inch.

        (III) Substance dispensing shall be metered and recorded within an accuracy of six or less cubic inches for every five gallons of product withdrawn.

        (IV) The measurement of any water level in the bottom of the tank shall be made to the nearest 1/8 inch at least once every 30 days, and appropriate adjustments to the inventory records shall be made.

  (2) Manual tank gauging. Manual tank gauging may be used as a tank release detection method, subject to the following limitations and requirements.

Cont'd...

Next Page Previous Page

Link to Texas Secretary of State Home Page | link to Texas Register home page | link to Texas Administrative Code home page | link to Open Meetings home page