RULE §3.13Casing, Cementing, Drilling, Well Control, and Completion Requirements

      (iii) Any alternate casing program shall include pumping sufficient cement to fill the annular space from the shoe or multi-stage tool to the ground surface. If cement is not circulated to the ground surface or the bottom of the cellar, the operator shall run a temperature survey or cement bond log. The appropriate district office shall be notified prior to running the required temperature survey or bond log. After the top of cement outside the casing is determined, the operator or the operator's representative shall contact the appropriate district director and obtain approval for the procedures to be used to perform any required additional cementing operations. Upon completion of the well, a cementing report shall be filed with the Commission on the prescribed form.

      (iv) Before parallel (nonconcentric) strings of pipe are cemented in a well, surface or intermediate casing must be set and cemented through the protection depth.

    (I) Mechanical integrity test of surface casing after drillout.

      (i) If the surface casing is exposed to more than 360 rotating hours after reaching total depth or the depth of the next casing string, the operator shall verify the integrity of the surface casing by using a casing evaluation tool or conducting a mechanical integrity test or equivalent Commission-approved casing evaluation method, unless otherwise approved by the district director.

      (ii) If a mechanical integrity test is conducted, the appropriate district office shall be notified at least eight hours before the test is conducted to give the district office an opportunity to witness the test. The operator shall use a chart of acceptable range (20% - 80% of full scale) or an electronic equivalent approved by the district director, and the surface casing shall be tested at a pump pressure in pounds per square inch (psi) calculated by multiplying the length of the true vertical depth in feet of the casing string by a factor of 0.5 psi per foot up to a maximum of 1,500 psi for a minimum of 30 minutes. A pressure test demonstrating less than a 10% pressure drop after 30 minutes constitutes confirmation of an acceptable pressure test. The appropriate district office shall be notified within 24 hours after a failed test. Completion operations may not re-commence until the district director approves a remediation plan and the operator successfully implements the approved plan, and successfully re-tests the surface casing.

  (2) Intermediate casing requirements for land wells and bay wells.

    (A) Cementing method. Each intermediate string of casing shall be cemented from the shoe to a point at least 600 feet (measured depth) above the shoe. If any productive zone, potential flow zone, or zone with corrosive formation fluids is open to the wellbore above the casing shoe, the casing shall be cemented;

      (i) if the top of cement is determined through calculation, from the shoe up to a point at least 600 feet (measured depth) above the top of the shallowest productive zone, potential flow zone, or zone with corrosive formation fluids;

      (ii) if the top of cement is determined through performance of a temperature survey, from the shoe up to a point at least 250 feet (measured depth) above the top of the shallowest productive zone, potential flow zone, or zone with corrosive formation fluids;

      (iii) if the top of cement is determined through performance of a cement evaluation log, from the shoe up to a point at least 100 feet (measured depth) above the top of the shallowest productive zone, potential flow zone, or zone with corrosive formation fluid; or

      (iv) to a point at least 200 feet (measured depth) above the shoe of the next shallower casing string that was set and cemented in the well (or to surface if the shoe is less than 200 feet from the surface); or

      (v) as otherwise approved by the district director.

    (B) Top of cement. The calculated or measured top of cement shall be indicated on the appropriate completion form required by §3.16 of this title (relating to Log and Completion or Plugging Report).

    (C) Alternate method. In the event the distance from the casing shoe to the top of the shallowest productive zone, potential flow zone, and/or zone with corrosive formation fluids make cementing, as specified above, impossible or impractical, the multi-stage process may be used to cement the casing in a manner that will effectively isolate and seal the zones to prevent fluid migration to or from such strata within the wellbore.

  (3) Production casing requirements for land wells and bay wells.

    (A) Centralizers. In deviated and horizontal holes, the operator shall provide centralization as necessary to ensure zonal isolation between the top of the interval to be completed and the shallower zones that require isolation.

    (B) Cementing method. The production string of casing shall be cemented by the pump and plug method, or another method approved by the Commission, with sufficient cement to fill the annular space back of the casing to the surface or to a point at least 600 feet above the shoe. If any productive zone, potential flow zone and/or zone with corrosive formation fluids is open to the wellbore above the casing shoe, the casing shall be cemented in a manner that effectively seals off all such zones by one of the methods specified for intermediate casing in paragraph (2) of this subsection. A float collar or other means to stop the cement plug shall be inserted in the casing string above the shoe. Cement shall be allowed to stand under pressure for a minimum of eight hours before drilling the plug or initiating casing pressure tests. In the event that the distance from the casing shoe to the top of the shallowest productive zone, potential flow zone and/or zone with corrosive formation fluids make cementing, as required above, impossible or impractical, the multi-stage process may be used to cement the casing in a manner that will effectively seal off all such zones, and prevent fluid migration to or from such zones within the wellbore. Uncemented casing is allowable within a producing reservoir provided the production casing is cemented in such a manner to effectively isolate and seal off that zone from all other productive zones in the wellbore as required by §3.7 of this title (relating to Strata To Be Sealed Off).

    (C) Reporting of top of cement. Calculated or measured top of cement shall be indicated on the appropriate completion form required by §3.16 of this title.

    (D) Isolation of gas/oil contact zones. The position of the gas-oil contact shall be determined by coring, electric log, or testing. The producing string shall be landed and cemented below the gas-oil contact, or set completely through and perforated in the oil-saturated portion of the reservoir below the gas-oil contact.

  (4) Tubing requirements for land wells and bay wells.

    (A) Tubing requirements for oil wells. All flowing oil wells shall be equipped with and produced through tubing. When tubing is run inside casing in any flowing oil well, the bottom of the tubing shall be at a point not higher than 100 feet (vertical depth) above the top of the producing interval nor more than 50 feet (vertical depth) above the top of the liner, if a liner is used, or 100 feet (vertical depth) above the kickoff point in a deviated or horizontal well. In a multiple zone structure, however, when an operator elects to equip a well in such a manner that small through-the-tubing type tools may be used to perforate, complete, plug back, or recomplete without the necessity of removing the installed tubing, the bottom of the tubing may be set at a distance up to, but not exceeding, 1,000 feet (vertical depth) above the top of the perforated or open-hole interval actually open for production into the wellbore.

    (B) Alternate tubing requirements. Alternate programs requesting a temporary exception pursuant to subsection (d) of this section to omit tubing from a flowing oil well may be authorized on an individual well basis by the appropriate district director. The district director shall deny the request if the operator has not demonstrated that the alternative tubing plan will achieve the intent as described in subsection (a)(1) of this section. If the proposal is rejected, the operator may request a review by the director of field operations. If the proposal is not approved administratively, the operator may request a hearing. An operator shall obtain approval of any alternative program before commencing operations.

(c) Casing, cementing, drilling, and completion requirements for offshore wells.

  (1) Casing. An offshore well shall be cased with at least three strings of pipe, in addition to such drive pipe as the operator may desire, which shall be set in accordance with the following program.

Cont'd...